Espola Road Safety Improvements Project

May 26, 2021 Update

The utility undergrounding for Espola Road has been ongoing. SDG&E completed their portion of the undergrounding work in March 2021. AT&T and Cox Communications both began their undergrounding at the end of 2020. Both AT&T and Cox are anticipated to complete their undergrounding work by July. Once their utilities are successfully converted to underground, SDG&E will remove the utility poles.

The City has completed the design plans for the pathways portion of the project. This project is currently being advertised for construction and will be awarded in July. Construction for the pathway improvements is expected to proceed as soon as the utility work is complete.

Project Background

The Espola Road Safety Improvements Project will improve safety for those who walk, jog, cycle or ride horses along the west side of Espola Road between Poway High School and Twin Peaks Road. 

All utility underground infrastructure has been installed. Much of the infrastructure for utilities undergrounding was designed to be installed within the proposed pathway along the west side of Espola Road. Infrastructure includes installation of conduit, vaults and above-grade structures. Due to conflicts with an existing high-pressure gas main, infrastructure in the northern portion was installed either in the street or on the east side of Espola Road. 

The next phase following infrastructure includes installing cables in new underground conduits and working on utility connections for individual properties along the undergrounding route. Both AT&T and Cox Communications have cabling work to complete once SDG&E is finished. During these phases there will be significantly less roadside activity and traffic impacts, but work is progressing nonetheless.

The three utility companies need to complete all conversion work prior to utility poles being removed. Pole removal is the last step in the undergrounding process and is expected to be complete by the summer of 2021.

The city has finalized design plans to re-bid the remaining portions of its work on the Espola Road Safety Improvements project. To avoid construction coordination conflicts the city will restart pathway improvement construction activities after the utility poles are removed. This portion of the project is anticipated to resume in the summer of 2021 and take approximately six months to complete.

Project Updates

Project updates will be provided on this page as well as posted on the City’s Nextdoor account and the City’s Twitter feed (@cityofpoway). If you don’t have a Twitter account, you can also search City of Poway at the Twitter website.