Espola Road Safety Improvements Project

November 22, 2021 Update

Construction for the pathway improvements is underway. The contractor has been busy at work removing the asphalt berm along the west side of Espola Road from Mountain Road to Northcrest Lane. They are also constructing the walls north of Evergreen Lane and installing conduit for the new street lights along the project area. Traffic control will be setup throughout the project area to shift southbound lanes to the east to provide a safe working area. Two lanes of traffic will be maintained while this work is taking place. The traffic signal at Espola Road & Del Poniente Road will operate in four-way flash when work is being performed in the immediate area. This will occur during working hours and outside of Poway High School’s drop-off and pick-up times.

Project Background

The Espola Road Safety Improvements Project will improve safety for those who walk, jog, cycle or ride horses along the west side of Espola Road between Poway High School and Twin Peaks Road. The first phase of the project is the undergrounding of utilities by SDG&E, Cox Communications, and AT&T. The second phase of the project is the City’s pathway improvements, which includes a decomposed granite pathway, new asphalt berm, grouted rock surface parkway, lodgepole fencing, and retaining walls.  

The utility undergrounding will begin with the installation of the underground infrastructure. Much of the infrastructure for utilities undergrounding was designed to be installed within the proposed pathway along the west side of Espola Road. Infrastructure includes installation of conduit, vaults and above grade structures. Due to conflicts with an existing high-pressure gas main, infrastructure in the northern portion was installed either in the street or on the east side of Espola Road. 

The next phase following infrastructure includes installing cables in new underground conduits and working on utility connections for individual properties along the undergrounding route. SDG&E will complete the installation of their underground cables first, followed by Cox and AT&T. During these phases there will be significantly less roadside activity and traffic impacts, but work is progressing nonetheless.

The three utility companies need to complete all conversion work prior to utility poles being removed. Pole removal is the last step in the undergrounding process and is expected to be complete by the summer of 2021.

While the utility undergrounding is taking place, the city will work with the design consultant to revise the design plans to re-bid the remaining portions of its work on the Espola Road Safety Improvements project. To avoid construction coordination conflicts the city will restart pathway improvement construction activities after the utility poles are removed. This portion of the project is anticipated to resume in the summer of 2021 and take approximately six months to complete.

Project Updates

Project updates will be provided on this page as well as posted on the City’s Nextdoor account and the City’s Twitter feed (@cityofpoway). If you don’t have a Twitter account, you can also search City of Poway at the Twitter website.